Construction Updates
Overview
- • We have cast the retaining wall for Tower A.
Tower A
- • We have cast the basement level columns.
Overview
- • We have finished casting half of the retaining wall for Tower A.
- • We are casting the remaining half of retaining wall for Tower A.
- • We are preparing shuttering work to cast the retaining walls for Tower B.
Tower A
- • We are preparing shuttering-work for the basement level columns.
Tower B
Overview
- • We have started working the retaining wall for Tower A.
Tower A
- • We have cast the raft level for Tower A. The foundation of this tower is now complete.
Tower B
- • We have cast the elevator pits.
- • We are preparing to cast the RCC for the raft level.
Overview
Tower A
- • We have completed the raft reinforcement for the foundation level.
- • We are ready to cast RCC in the foundation level.
Tower B
- • We have cast remaining portion of PCC for the foundation level.
Overview
Tower A
- • We have excavated the basement and have cast the PCC.
- • We are assembling the raft reinforcement.
Tower B
- • We have excavated the basement level.
- • We have cast half of PCC for foundation level.
- • We are preparing to cast the remaining PCC for the foundation level.