Tower A
We have completed brick-work for Level 15.
We have finished internal plaster work for Level 11.
We have finished conduit-work for Level 12.
Tower B
We have finished brick-work for Level 10.
We have finished conduit-work for Level 4.
Tower C
We have cast half of the columns for Level 6.
We are preparing shuttering work for remaining columns for Level 6.
Tower D
We have cast Level 5.
We have casted half of the columns for Level 6.
We are preparing shuttering work for remaining columns for Level 6.
Overview
Tower A
We are completed brick-work for Level 15.
We have finished internal plaster work for Level 10.
We have finished conduit-work for Level 11.
Tower B
We have finished brick-work for Level 9.
We have completed internal plaster work for Level 6.
Tower C
We have cast Level 5.
Tower D
We are casting Level 5.
Overview
Tower A
We have finished brick-work for half of Level 15.
We have finished internal plaster work for three-quarters of Level 8.
Tower B
We have finished brick-work for Level 8.
Tower C
We are ready to cast Level 5.
Tower D
We are ready to cast Level 5.
Overview
Tower A
We have finished brick-work for Level 14.
We have finished internal plaster work till Level 4.
Tower B
We have finished brick-work for Level 8.
Tower C
We are ready to cast Level 5.
Tower D
We have cast Level 4.
We are preparing to cast columns for Level 4.
Overview
Tower A
• We are finishing brick-work for Level 13.
• We have finished internal plaster work till Level 4.
Tower B
• We have finished brick-work for Level 8.
Tower C
• We have cast Level 4.
• We have cast columns for Level 5.
Tower D
• We have cast Level 3.
• We are preparing to cast columns for Level 4.
Overview
Tower A
• We have completed shuttering work for Level 18.
• We have finished brick-work for Level 12.
• We have finished internal plaster work till Level 4.
Tower B
• We have completed shuttering work for Level 18.
• We have finished brick-work for Level 7.
Tower C
• We have cast Level 4.
• We have cast columns for Level 5.
Tower D
• We have cast Level 3.
• We are preparing to cast columns for Level 4.
Overview
Tower A
• We have cast columns for Level 18.
•We have started shuttering work for Level 18.
• We are finishing brick-work for Level 12.
Tower B
• We have cast Level 17.
• We are preparing columns for Level 18.
• We are finishing brick-work for Level 6.
Tower C
• We are preparing columns to cast Level 5.
• We are preparing to cast the Ground Floor slab.
Tower D
• We have casting Level 3.
Overview
Tower A
• We have casted Level 17.
• We are preparing columns for Level 18.
• We are finishing brick-work for Level 11.
Tower B
• We have casted Level 16.
• We are preparing columns for Level 17.
• We are finishing brick-work for Level 5.
Tower C
• We have casted Level 4.
• We are preparing columns to cast Level 5.
Tower D
• We have casted Level 2.
• We have casted columns for Level 3 on half of Level 2.
• We are preparing columns to cast the remaining portion of Level 3.
Overview
Tower A
• We have casted Level 15.
• We are preparing columns for Level 16.
• We are finishing brick-work for Level 11.
Tower B
• We are casting Level 15.
• We are finishing brick-work for Level 5.
Tower C
• We have casted Level 3.
• We are preparing columns to cast Level 4.
Tower D
• We have casted Level 1.
• We are preparing columns to cast Level 2.
Overview
Tower A
We have completed the conduiting work for Level 14.
We are preparing to cast Level 1.
Tower B
We are casting Level 13.
Tower C
We have casted Level 2.
We are preparing to cast Level 3.
Tower D
We have casted half of Level 1.
We are preparing to cast the remaining portion of Level 1.