Construction Updates

Select year

Disclaimer : All updates are corresponding to the end of the month.

Tower A & B

  • We have finished casting Level 13.
  • Internal brickwork for Apartments A-301, A-302, A-303, A-304, A-305 & A-306 has started.
  • Internal brickwork for Apartments B-201, B-202, B-203 & B-204 has been completed.

Tower C & D

  • Shuttering work of 2nd elevator (in Tower D) retaining wall is in progress.

Disclaimer : All updates are corresponding to the end of the month.

Overview


Tower A

  • We have finished casting Level 12.
  • We are preparing to cast columns for Level 13.
  • Internal brickwork for Apartments A-201, A-202, A-203, A-204, A-205 & A-206 has started.

Tower B

  • We have finished casting Level 12.

Tower C

  • We have finished casting Level 3.

Tower D

  • We have finished casting Level 2.
  • We are casting the retaining wall for Tower D.
  • We are installing the flange for the Underground Water Tank in Tower D.

Disclaimer : All updates are corresponding to the end of the month.

Overview


Tower A

  • We have finished casting Level 11.
  • We are preparing to cast columns for Level 12.
  • We have finished the installation of the Materials Hoist.

Tower B

  • We have finished casting Level 10.
  • We are preparing to cast of Level 11.

Tower C

  • We are preparing to cast the Internal Driveway.
  • We are finishing casting Level 2.
  • We have finished casting the Project Pump Room.
  • We are preparing to cast Level 3.

Tower D

  • We have finished casting Level 1.
  • We are casting the columns for Level 2.

Overview


Tower A

  • We have finished casting Level 10.
  • We are preparing to cast columns for Level 11.
  • We are finishing the installation of the Materials Hoist.

Tower B

  • We have finished casting Level 9.
  • We are preparing to cast of Level 10.

Tower C

  • We are preparing to cast the Internal Driveway.
  • We are finishing the conduit work on remaining part of Level 1.
  • We are preparing to cast the Project Pump Room (Level 1 component).
  • We are preparing to cast remaining part of Level 2.

Overview


Tower A

  • We are preparing to cast columns for Level 8.

Tower B

  • We are casting Level 8.

Tower C

  • We have finished casting part of Level 1.
  • We have finished casting part of Pump Room (Basement Component).
  • We are about to cast part of Level 2.

Tower D

  • We are finishing the iron grid-work for the Foundation Level.

Overview


Tower A

  • We are preparing to cast Level 7.

Tower B

  • We are preparing to cast Level 6.

Tower C

  • We are preparing to cast the Level 1.
  • We are finishing the layout of the project Pump Room (Basement Component).