Construction Updates

Amadeus

scroll down
Latest Updates in Amadeus

2018

September

Tower A:

  • We have cast Level 20.
  • We have completed brick-work till Level 14.

Tower B

  • We are preparing to cast Level 17.
  • We have completed brick-work for Level 12.

Tower C

  • We have completed brick-work till Level 17.

Overview

  • We have started preparation work on the project landscape in front of the driveway.
  • We have finished false ceiling work for Tower C lobby.
  • We have started the stone-work for Tower C lobby.
  • We are installing the glazing for Tower C lobby.
  • We have temporarily moved the sales office to Level 3 beside the show apartment
  • We are ready to cast the podium roof (front) and pedestrian walk-way between Towers B & C.

August

Tower A:

  • We have cast half of Level 19.
  • We have completed brick-work till Level 13.
  • We have started brick-work for Level 14.

Tower B

  • We have cast the remaining half of Level 16.
  • We have completed brick-work for Level 12.

Overview

  • We have temporarily moved the sales office to Level 3 beside the show apartment.
  • We have started preparation work on the project landscape in front of the driveway.
  • We have started the stone-work for Tower C lobby.
  • We are ready to install the glazing for Tower C lobby.
  • We have cast the connecting slab for the driveway level between Towers B & C.
  • We have finished the shuttering work for the podium roof (front) and pedestrian walk-way between Towers B & C.
  • We are ready to cast the podium roof (front) and pedestrian walk-way between Towers B & C.